Groundworks, drainage, RC Sub-structure and Superstructure for the redevelopment of Garth Hill College. The package comprised four multi storey teaching blocks and a gym/sports hall. All finishes to concrete walls/columns were Fine Smooth Finish. DCL advised the client on the major benefits of Bamtec Reinforcement for this particular project, the result being a 20% time saving on the RC Frame works.

Client:

Bracknell-Forest

Main Contractor:

Mace Plus

Architect:

Scott Brownrigg

Engineer:

Adams Kara Taylor

Value:

£3.6M

Duration:

34 weeks

Completed:

2011